Resource Mobilization, Fundraising And Project Management June/July 2014

Exam year;June/July 2014

Free knec college past papers

Social work and community development past papers

THE KENYA NATIONAL EXAMINATIONS COUNCIL
DIPLOMA IN SOCIAL WORK AND COMMUNITY DEVELOPMENT
MODULE II
RESOURCE MOBILIZATION, FUNDRAISING AND PROJECT MANAGEMENT.

SECTION A: RESOURCE MOBILIZATION AND FUNDRAISING
1) Explain the contents of each of the following section of the project proposal outline:
i. Project justification;
ii. Problem statement;
iii. Anticipated outcomes or results;
iv. Work scope or implemented plan;
v. Reporting; ( 10 marks)
(b) Explain five benefits of strategic planning in fundraising. ( 10 marks)
2) ( a) Describe three tools used in fundraising. ( 6 marks)
(b) Explain six principles of fundraising. ( 14 marks)
3) ( a) Explain four techniques of mobilizing financial resources. ( 8 marks)
(b) State and explain six income generating activities used for fundraising.( 12marks)
4) (a) Explain the meaning of each of the following terms used in resource mobilization.
i. Philanthropy
ii. Resource
iii. Resource mobilization
iv. Financial management
v. Funding ( 10 marks)
(b) State and explain five types of donors for resource mobilization. ( 10 marks)

SECTION B: PROJECT MANAGEMENT
5) ( a) Describe each of the following types of project appraisal:
i. Market;
ii. Technical;
iii. Financial;
iv. Economic; (8 mark)
(b) State and explain six factors influencing the selection of community project ideas.
(12 marks)
6) (a) State and explain four sources of risk in project management (8 marks)
(b) Explain six pre-requisites for successful project implementation.(12 marks)
7) (a) Differentiate between the following:
i. Direct project management approach and participatory project management approach;
ii. Project termination and project abandonment. ( 8 marks)
8) (a) Explain four forms of community participation in project management.(8 marks)
(b) Explain six common causes of project failure. (12 marks)